Hi - I need to consolidate our many vCenters. Some are used by vCD 5.1. Migrating hosts etc to a new vCenter is the easy bit but how about vCD? I'm not sure how to move all resources across to a new vCenter in vCD.
If I was just adding a new vCenter with new storage etc I could use elastic pVDCs to add the new resources to an existing pVDC, migrate the vApps and then remove the original resource pool(s) but that's not quite what I'm doing - I will be moving hosts (along with the VMs and storage etc to a new vCenter.
Could I do something like this:
- Build the new vcenter
- move one of the hosts to it
- create a new resource pool
- create a pVDC from it (although it would have the same storage attached?)
- merge this new pVDC with the existing one then migrate vApps over to it?